Completed client project. The owners came to us to add a shower to the partial bath in their 1,428-square-foot, two-bedroom home on Hilldale Drive in San Anselmo. The house has one full bath and one partial bath. Built in 1951, it is a single-story wood-frame home with a low-pitched composition roof, large windows, and an unfinished basement. The great room joins the living and dining areas around a centered fireplace, while the kitchen stays separate but visually connected through its window and breakfast nook. One shower served the household, and the partial bath could not help with morning routines. Our first question was how the partial bath sat over the unfinished basement, and whether the existing drain route made a second shower practical without changing the house’s footprint.
The photographs on this page are from the Designed & Curated portfolio and show finishes we have used on other projects. They are not photographs of this house.
The partial bath above the unfinished basement
On site, we measured the partial bath and found that its floor sat above accessible unfinished basement space. We traced the existing waste line from below and found a route to the public sewer connection that let us add a shower without extending the house into the garden. That finding followed from the home’s one-story construction and unfinished basement, but we still needed to see the actual route before settling the layout. We kept the toilet and sink in place, fitted the shower within the existing room, and maintained clear access through the doorway.
The main bathroom already had a tub with a shower over it, tile finishes, and a low-flow toilet. It remained outside the construction work. We chose a restrained tile and paint palette for the new shower so the two bathrooms felt related without making them identical. The kitchen’s white upper cabinets, blue lower cabinets, quartz counters, and matte black hardware give the house a contemporary note against its mid-century wood floors and soft neutral walls. We carried that balance into the partial bath, with a simple contrast rather than another strong color statement. The new shower gave the household another place to bathe, while the existing full bath retained its tub.
The kitchen stayed connected, not enlarged
The kitchen remained outside the construction scope, so we did not take space from the great room or backyard. It already had white upper cabinetry, bold blue lower cabinets, quartz countertops, a subway-tile backsplash, ceramic tile flooring, stainless steel appliances, and a breakfast nook with wine storage and seating. We left that arrangement intact while concentrating the construction work in the partial bath. The kitchen remained visually linked to the great room through its window and counter nook, and the living and dining areas kept their hardwood floors and direct access through the large sliding glass door.
That division mattered on this lot. The property measures about 4,874 square feet, with a south-facing, landscaped backyard, privacy planting, and views toward Mt. Tam. We kept the garden and its auto sprinklers outside the work area rather than adding a new wing or taking away outdoor space. The great room’s fireplace, gas-piped with an insert, remained its focal point, and the kitchen’s gas range stayed where it was. The central gas heating and ceiling fans also stayed untouched, since the bathroom work did not call for changes to the house’s heating or cooling.
The unfinished basement gave us access to the plumbing route without extending the home’s footprint. The public sewer connection served the new fixture, and the composition roof and single-story roofline remained unchanged. We kept the great room, kitchen, and bedroom floors out of the bathroom work zone. The large windows continued to bring natural light into the living room and primary bedroom, while the existing hardwood, kitchen tile, and soft neutral paint palette remained in place.
The added shower and the daily route
The basement access let us complete the shower plumbing from below, and the public sewer service provided a connection within the house’s existing systems. We kept the main full bath available as the other bathing space and left the great room, kitchen, and bedroom floors out of the bathroom work zone. The backyard, its landscaping, and the house’s existing roofline also remained untouched. The project focused on improving the partial bath without changing the kitchen layout or the house’s heating and cooling systems.
After the work, the household had a shower in the former partial bath as well as the tub-shower in the full bath. That changed the morning routine without taking a bedroom, changing the kitchen layout, or reducing the garden. The kitchen retained its breakfast area and existing storage, and the great room continued to open directly to the backyard. The house worked better through a change inside its existing envelope, not through an addition.
Get in touch to talk about your home.